Clear Creek Storage Company, LLC |
|
Third Revised Sheet No. 76 : Effective |
FERC Gas Tariff |
|
Supersedes Second Revised Sheet No. 76 |
Clear Creek Storage Company, LLC |
GENERAL TERMS AND CONDITIONS
(Continued)
conditions requiring an OFO including (i) physical inability to
inject or withdraw gas due to operational constraints, (ii)
force majeure as described in Section 21 of these General Terms
and Conditions, (iii) unexpected operating conditions that
endanger the integrity of the storage system.
Clear Creek may issue an OFO prohibiting or requiring
receipt or delivery of Gas, if necessary, to protect the
integrity of the reservoir, for testing, to ensure needed
deliverability, to cure storage account imbalances or to deal
with any operational difficulties. A Customer shall be
afforded reasonable opportunity, consistent with existing
operational conditions, to respond to Clear Creeks OFO.
If an OFO is required, Clear Creek shall issue an OFO to
Customer as expeditiously as is reasonably practicable under
the circumstances through the affected Customers choice of
electronic notice delivery mechanism according to Section 2.6
of these General Terms and Conditions. Each OFO will contain
the following information:
(1) The time and date of issuance.
(2) The party or parties receiving the OFO.
(3) The nature of the problem to be addressed.
(4) The action the customer is expected to take.
(5) The time the OFO is considered to be effective
and the time by which the Customer must comply with the OFO.
(6) The duration of the OFO. If none is specified,
the OFO will be effective until further notice.
(7) The quantity of Gas required to remedy the
operational condition requiring the issuance of the OFO, if
applicable.
(8) Any other items Clear Creek may reasonably
require to ensure the effectiveness of the OFO.
Issued by: M.B. McGinley, Vice President |
Issue date: 07/30/02 |
|
Effective date: 10/01/02 |