Clear Creek Storage Company, LLC |
|
Original Sheet No. 57 : Effective |
FERC Gas Tariff |
|
|
Clear Creek Storage Company, LLC |
GENERAL TERMS AND CONDITIONS
(Continued)
(2) With respect to the processing of requests for
increases during the intraday nomination/confirmation
process, in the absence of Agreement to the contrary, the
lesser of the confirmation quantities should be the new
confirmed quantity. If there is no response to a request
for confirmation or an unsolicited confirmation response,
the previously scheduled quantity shall be the new confirmed
quantity.
(3) With respect to the processing of requests for
decreases during the intraday nomination/confirmation
process, in the absence of agreement to the contrary, the
lesser of the confirmation quantities should be the new
confirmed quantity, but in any event no less than the
elapsed-prorated-scheduled quantity. If there is no
response to a request for confirmation or an unsolicited
confirmation response, the greater of the confirmation
quantity or the elapsed-prorated-scheduled quantity shall be
the new confirmed quantity.
(4) With respect to Section 10.7 (1), (2) and (3)
above, if there is no response to a request for confirmation
or an unsolicited confirmation response, Clear Creek shall
provide the Customer with the following information to
explain why the nomination failed, as applicable:
(a) Clear Creek did not conduct the confirmation;
(b) Customer is told by Clear Creek that the
upstream confirming party did not conduct the confirmation;
(c) Customer is told by Clear Creek that the
upstream Customer did not have the Gas or submit the
nomination;
(d) Customer is told by Clear Creek that the
downstream confirming party did not conduct the
confirmation;
(e) Customer is told by Clear Creek that the
downstream Customer did not have the market or submit the
nomination.
This information shall be imparted to the Customer on
the scheduled quantity document.
Issued by: M.B. McGinley, Vice President |
Issue date: 03/30/00 |
|
Effective date: 06/01/00 |